CASE STUDY #4 – Conversion of Water / Sewer from Private Well/Septic to Public Water/Sewer
Renaud Consulting was engaged for the implementation of a water & sewer conversion project at a 172,820-square foot shopping center. Renaud provided oversight of the abandonment of seven (7) on-site septic systems and the installation of 2,397-linear feet of sewer pipe with 17 manholes and 10 clean outs. Renaud also decommissioned two on-site water supply wells, and installed 82-linear feet of new 8-inch diameter water main, a primary water meter, and new fire hydrants, all of which was connected to the Anne Arundel County public water supply system. Upon completion of the sewer & water conversion, Renaud completed the project by milling and paving the entire parking lot, re-striping the new asphalt, upgrading multiple landscaping beds, and painting and updating the center’s pylon sign.